Egenda Ege Energy Production Co.
Alaçatı Wind Power Plant
Board Of Directors |
President |
: |
Cem Bakioğlu |
Vice President |
: |
Samim Sivri |
Members |
: |
Murat Demirer, Süleyman Kamil Şenocak, Ahmet Metin Tarhan, Ahmet Sırrı Yırcalı, Koray Kıymaz, Selçuk Borovalı, Hüseyin Metin Tuncay |
Company İnformation |
Legal Entity |
: |
Egenda Ege Energy Production Co. |
Capital |
: |
210.000.000 TL |
Installed Power |
: |
16 MWm / 16 MWe |
Type |
: |
Wind |
Location |
: |
İzmir / Çeşme |
Operation Model/Duration |
: |
03.06.2016 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
E82-E4/Enercon |
Number Of Unit |
: |
8 |
Wint Class |
: |
II |
Connection Type |
: |
MV |
Egenda Ege Energy Production Co.
Germiyan Wind Power Plant
Board Of Directors |
President |
: |
Cem Bakioğlu |
Vice President |
: |
Samim Sivri |
Members |
: |
Murat Demirer, Süleyman Kamil Şenocak, Ahmet Metin Tarhan, Ahmet Sırrı Yırcalı, Koray Kıymaz, Selçuk Borovalı, Hüseyin Metin Tuncay |
Company İnformation |
Legal Entity |
: |
Egenda Ege Energy Production Co. |
Capital |
: |
210.000.000 TL |
Installed Power |
: |
12 MWh / 10.8 MWe |
Type |
: |
Wind |
Location |
: |
Çeşme / İzmir |
Operation Model/Duration |
: |
06.05.2016 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
E82-E4/Enercon |
Number Of Unit |
: |
6 |
Wint Class |
: |
II |
Connection Type |
: |
MV |
Egenda Ege Energy Production Co.
Mordoğan Wind Power Plant
Board Of Directors |
President |
: |
Cem Bakioğlu |
Vice President |
: |
Samim Sivri |
Members |
: |
Murat Demirer, Süleyman Kamil Şenocak, Ahmet Metin Tarhan, Ahmet Sırrı Yırcalı, Koray Kıymaz, Selçuk Borovalı, Hüseyin Metin Tuncay |
Company İnformation |
Legal Entity |
: |
Egenda Ege Energy Production Co. |
Capital |
: |
210.000.000TL |
Installed Power |
: |
15 MWm / 13,8 MWe |
Type |
: |
Wind |
Location |
: |
İzmir / Karaburun |
Operation Model/Duration |
: |
24.06.2016 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
E82-E4/Enercon |
Number Of Unit |
: |
5 |
Wint Class |
: |
I |
Connection Type |
: |
MV |
Egenda Ege Energy Production Co.
Urla Wind Power Plant
Board Of Directors |
President |
: |
Cem Bakioğlu |
Vice President |
: |
Samim Sivri |
Members |
: |
Murat Demirer, Süleyman Kamil Şenocak, Ahmet Metin Tarhan, Ahmet Sırrı Yırcalı, Koray Kıymaz, Selçuk Borovalı, Hüseyin Metin Tuncay |
Company İnformation |
Legal Entity |
: |
Egenda Ege Energy Production Co. |
Capital |
: |
210.000.000 TL |
Installed Power |
: |
15 MWm / 13 MWe |
Type |
: |
Wind |
Location |
: |
İzmir / Urla |
Operation Model/Duration |
: |
27.05.2016 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
E82-E4/Enercon |
Number Of Unit |
: |
5 |
Wint Class |
: |
I |
Connection Type |
: |
MV |
Yaylaköy WPP Electricity Production Co.
Yaylaköy WPP Power Plant
Board Of Directors |
President |
: |
Hüseyin Metin Tuncay |
Vice President |
: |
Dalyan Ahmet Ersin |
Members |
: |
Burak Levent Doruk |
Company İnformation |
Legal Entity |
: |
Yaylaköy WPP Electricity Production Co. |
Capital |
: |
10.000.000 TL |
Installed Power |
: |
15 MWm / 15 MWe |
Type |
: |
Wind |
Location |
: |
Karaburun/İZMİR |
Operation Model/Duration |
: |
25.03.2016 |
Unit Type/Manufacturer |
: |
Production /49 Years |
Unit Type |
: |
E82-E4/Enercon |
Number Of Unit |
: |
5 |
Wint Class |
: |
I |
Connection Type |
: |
MV |
Tirenda Tire Electricity Production Co.
Natural Gas Power Plant
Board Of Directors |
President |
: |
Hüseyin Metin Tuncay |
Vice President |
: |
Dalyan Ahmet Ersin |
Members |
: |
|
Company İnformation |
Legal Entity |
: |
Tirenda Tire Electricity Production Co. |
Capital |
: |
91.250.000 TL |
Installed Power |
: |
58,38 MWe |
Type |
: |
Natural Gas |
Location |
: |
İzmir/Tire |
Operation Model/Duration |
: |
30.12.2011 |
Unit Type/Manufacturer |
: |
Production/ 49 Years |
Unit Type |
: |
Natural Gas Engine (Wartsila) |
Number Of Unit |
: |
6 (6x9,73 MWe) |
Wint Class |
: |
|
Connection Type |
: |
154 kV-3km Tire TM |
Su Enerji HPP Electricity Production Co.
Çaygören HPP Hydroelectric Plant
Board Of Directors |
President |
: |
Hüseyin Metin Tuncay |
Vice President |
: |
Dalyan Ahmet Ersin |
Members |
: |
|
Company İnformation |
Legal Entity |
: |
Su Enerji HPP Electricity Production Co. |
Capital |
: |
3.000.000 TL |
Installed Power |
: |
4,6 MWe |
Type |
: |
Hydroelectric |
Location |
: |
Sındırgı/Balıkesir |
Operation Model/Duration |
: |
27.06.2006 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
Francis (Horizantal) Vatech |
Number Of Unit |
: |
1x3,0 MWe + 1x1,6 MWe |
Net Head and Flow Rate |
: |
46 mt, 11.5 m3/second. |
Connection Type |
: |
34.5 KV - 4 km DM |
Akçay HPP Electricity Production Co.
Hydroelectric power plant
Board Of Directors |
President |
: |
Hüseyin Metin Tuncay |
Vice President |
: |
|
Members |
: |
|
Company İnformation |
Legal Entity |
: |
Akçay HPP Electricity Production Co. |
Capital |
: |
26.750.000 TL |
Installed Power |
: |
28.8 MWe |
Type |
: |
Hydroelectric (Channel type) |
Location |
: |
Bozdoğan/Aydın |
Operation Model/Duration |
: |
14.08.2009 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
Francis (Vertical) HRC |
Number Of Unit |
: |
2x11,6 MWe + 1x5.6 MWe |
Net Head and Flow Rate |
: |
86.5 mt - 36m3/second. |
Connection Type |
: |
31.5 kV - 12.2 km DM |
Egenda Ege Energy Production Co.
Eğlence I HPP Hydroelectric Power Plant
Board Of Directors |
President |
: |
Cem Bakioğlu |
Vice President |
: |
Samim Sivri |
Members |
: |
Murat Demirer, Süleyman Kamil Şenocak, Ahmet Metin Tarhan, Ahmet Sırrı Yırcalı, Koray Kıymaz, Selçuk Borovalı, Hüseyin Metin Tuncay |
Company İnformation |
Legal Entity |
: |
Egenda Ege Energy Production Co. |
Capital |
: |
210.000.000 TL |
Installed Power |
: |
43,5 MWe |
Type |
: |
Hydroelectric (River type) |
Location |
: |
Adana/Karaisalı |
Operation Model/Duration |
: |
13.06.2013 |
Unit Type/Manufacturer |
: |
Production / 49 Years |
Unit Type |
: |
Francis (Vertical) Flovel |
Number Of Unit |
: |
3 (8,25+2x17,20 MWe) |
Net Head and Flow Rate |
: |
276 mt - 17.4 m3/second. |
Connection Type |
: |
154 kV-2,6 km E2 TM |
Egenda Ege Energy Production Co.
Eglence II HPP Hydroelectric Power Plant
Board Of Directors |
President |
: |
Cem Bakioğlu |
Vice President |
: |
Samim Sivri |
Members |
: |
Murat Demirer, Süleyman Kamil Şenocak, Ahmet Metin Tarhan, Ahmet Sırrı Yırcalı, Koray Kıymaz, Selçuk Borovalı, Hüseyin Metin Tuncay |
Company İnformation |
Legal Entity |
: |
Egenda Ege Energy Production Co. |
Capital |
: |
210.000.000 TL |
Installed Power |
: |
27,2 MWe |
Type |
: |
Hydroelectric (River Type) |
Location |
: |
Adana/Karaisalı |
Operation Model/Duration |
: |
10.04.2013 |
Unit Type/Manufacturer |
: |
Production 49 / Years |
Unit Type |
: |
Francis (Horizantal) Flovel |
Number Of Unit |
: |
3 (5+2x10,50 MWe) |
Net Head and Flow Rate |
: |
169 mt - 17.4 m3/second. |
Connection Type |
: |
154 kV - 19,8 km Tm |
Tuzla Geothermal Energy Co.
Tuzla GPP Geothermal Power Plant
Board Of Directors |
President |
: |
Hüseyin Metin Tuncay |
Vice President |
: |
Dalyan Ahmet Ersin |
Members |
: |
|
Company İnformation |
Legal Entity |
: |
Tuzla Geothermal Energy Co. |
Capital |
: |
27.600.000 TL |
Installed Power |
: |
7.5 MWe |
Type |
: |
Geothermal |
Location |
: |
Çanakkale/Ayvacık |
Operation Model/Duration |
: |
13.01.2010 |
Unit Type/Manufacturer |
: |
Production 40 /Years |
Unit Type |
: |
ORC/ORMAT |
Number Of Unit |
: |
|
Connection Type |
: |
34.5 kV - 1km Root H. |
Board Of Directors |
President |
: |
|
Vice President |
: |
|
Members |
: |
|
Company İnformation |
Legal Entity |
: |
|
Capital |
: |
|
Installed Power |
: |
|
Type |
: |
|
Location |
: |
|
Operation Model/Duration |
: |
|
Unit Type/Manufacturer |
: |
|
Unit Type |
: |
|
Number Of Unit |
: |
|
Net Head and Flow Rate |
: |
|
Connection Type |
: |
|
RESİYTE Electricity Production Co.
RESİYTE DOES NOT HAVE PLANT.